TT-Line QON Response (4 October 2024)
Letter to Chair from Dr Damian Bugg (Interim Chair) dated 4 October 2024
Attachments in Date Order
Memorandum of Understanding - Eastern Side of the Port of Devonport (24 December 2019)
Cost Estimate Summary - TT Line Bespoke Capital Only (18 May 2020)
Email from TasPorts to TT-Line (22 May 2020) - TT-Line Bespoke Capital
Letter from TT-Line to TasPorts (29 May 2020) - Response to Proposed Pricing
Letter from TasPorts to TT-Line (2 June 2020) - Offer to Transfer Land
Email from TT-Line to TasPorts (24 June 2020) - TT-Line Board Decisions
Email from TasPorts to TT-Line (24 June 2020) - Response to TT-Line Board Decisions
Internal TT-Line notes on TasPorts (28 June 2020)
Minutes of TT-Line Meeting with TasPorts (29 June 2020)
Letter from TasPorts to TT-Line (1 December 2020) - Termination of Memorandum of Understanding
Letter from TasPorts to TT-Line (27 January 2021) - Re Termination of Memorandum of Understanding
Executed Contract Term Sheet (29 June 2021)
Minutes of Minister's Meeting (19 May 2022)
Letter to Deputy Premier from TT-Line (25 May 2022) - New Ship Build Contract
Overlay 1 (1 November 2023) - Devonport E3 Berth Works
Email from TasPorts to Deputy Premier (20 December 2023) - TasPorts and TT-Line Schedule